Simi Valley Metrolink Station Parking Lot Rehab and ADA Upgrades |
Description: Removal of asphalt, replacement of asphalt, landscaping, irrigation upgrades, sidewalk work, striping, and signage.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Ventura |
Zip Code | 93003 |
Senate District |
27 |
Assembly District | 38 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 5 | 5 |
Reduced Operating/Maintenance Cost | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
STEPHANIE YOUNG | (805) 642-1591 X108 | SYOUNG@GOVENTURA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $5 | $5 | ||||
PTMISEA-99313 |
$550 | $-79 | $471 | ||||
Non-bond Funding | |||||||
Total**** | $550 | $-73 | $477 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$25 | $-25 | $0 | $11 | $11 | $-11 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$525 | $-48 | $477 | $465 | $465 | $11 | |
Total* | $550 | $-73 | $477 | $477 | $477 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/14/2013 03/11/2013 |
03/20/2014 03/20/2014 |
09/26/2013 10/07/2013 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/15/2013 11/18/2013 |
03/20/2014 03/24/2015 |
10/14/2013 08/25/2014 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/14/2014 06/30/2014 |
03/24/2015 03/24/2015 |
03/09/2015 04/17/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/14/2014 08/25/2014 |
07/26/2016 07/26/2016 |
01/05/2016 04/13/2016 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 5 | 5 |
Reduced Operating/Maintenance Cost | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$550,000 |
Current Approved: |
$471,487 |
Actual Expenditures: |
$471,487 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31