Expansion of Metrolink Parking Lot and Slurry Seal of Existing Lot

Description: Expansion of Metrolink North parking lot by 55 spaces and slury seal of existing lot. Project also includes security cameras, lighting, and a new driveway connecting lot to street.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 35
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Increased Ridership  20      
Reduced Emissions  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHANIE YOUNG (805) 642-1591 X108   SYOUNG@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $100 $100
PTMISEA-99313
$317 $802 $1,119
Non-bond Funding
 
Total**** $317 $902 $1,219

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$33 $0 $33 $107 $107 $-74
Right of Way
$0 $0 $0 $4 $4 $-4
Construction
$284 $902 $1,186 $851 $851 $335
 
Total* $317 $902 $1,219 $962 $962 $257

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2013 

11/01/2013 
03/01/2016 

09/21/2016 
02/01/2016 

10/01/2016 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2013 

01/01/2014 
09/21/2016 

10/28/2021 
10/01/2016 

09/01/2021 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2014 

03/31/2014 
10/28/2021 

02/15/2023 
01/01/2022 

09/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2014 

07/01/2014 
02/15/2023 

02/15/2023 
09/01/2022 

02/28/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Increased Ridership 20
Reduced Emissions 20

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31