Modernization Improvement for Route Match of DART Fixed Routes

Description: Modernization Improvement for Route Match of DART Fixed Routes

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Delano
Zip Code 93216
 
Senate District
16
Assembly District 32
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  75    10  
Increased Ridership  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
NOEMI ZAMUDIO (661) 720-2210   NZAMUDIO@CITYOFDELANO.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$20 $0 $20
PTMISEA-99314
$16 $0 $16
Non-bond Funding
Local**
$0 $21 $21
 
Total**** $36 $22 $58

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$36 $22 $58 $58 $58 $0
 
Total* $36 $22 $58 $58 $58 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2013 

12/31/2013 
 

 
11/01/2014 

02/28/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
01/31/2014 

02/01/2014 
 

10/29/2014 
03/31/2015 

04/30/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 75 10
Increased Ridership 25

Bond Funding Cost
Adopted:
$36,296
Current Approved:
$36,296
Actual Expenditures:
$36,296

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31