Town of Truckee - Construct Bus Pull Out & Shelter on Estates Drive

Description: Construct a bus pull out & shelter on Estates Drive

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Nevada City
Zip Code 95959
 
Senate District
03
Assembly District 01
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    20  
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE WOODMAN (530) 265-3202   MWOODMAN@NCCN.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$15 $0 $15
PTMISEA-99313
$60 $0 $60
Non-bond Funding
State/Federal*
$190 $0 $190
Local**
$14 $-0 $14
 
Total**** $279 $0 $279

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$279 $0 $279 $279 $279 $0
 
Total* $279 $0 $279 $279 $279 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2020 

01/31/2021 
 

 
09/01/2020 

01/31/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
03/31/2021 

04/30/2021 
 

 
03/31/2021 

05/31/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 20
Increased Ridership 10

Bond Funding Cost
Adopted:
$74,918
Current Approved:
$59,981
Actual Expenditures:
$59,981

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31