Caltrans Logo

Replacement DAR Vehicles

Description: Replacement of up to eight DAR vans and cutaways.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
27
Assembly District 44
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20      
Reduced Emissions  20    48  
Reduced Operating/Maintenance Cost  40      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHANIE YOUNG (805) 642-1591 X108   SYOUNG@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$800 $0 $800
Non-bond Funding
 
Total**** $800 $3 $803

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$800 $3 $803 $806 $806 $-3
 
Total* $800 $3 $803 $806 $806 $-3

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2014 

10/30/2014 
 

 
04/30/2014 

10/30/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
11/30/2014 

12/30/2014 
 

03/17/2015 
11/30/2014 

02/28/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Reduced Emissions 20 48
Reduced Operating/Maintenance Cost 40

Bond Funding Cost
Adopted:
$800,000
Current Approved:
$800,000
Actual Expenditures:
$800,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31