City of Colfax Transit Center Pedestrian/Bike Access Improvements

Description: Design and construction of pedestrian and bike access improvements connecting downtown Colfax with the Colfax Transit Center.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01
Assembly District 01
Congressional District 01
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4090   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$67 $0 $67
Non-bond Funding
State/Federal*
$0 $154 $154
 
Total**** $67 $154 $221

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$67 $154 $221 $221 $221 $0
 
Total* $67 $154 $221 $221 $221 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

04/28/2016 
 

01/31/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

02/01/2014 
 

 
 

02/01/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2014 

03/07/2014 
 

04/28/2016 
02/01/2014 

03/07/2014 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2014 

11/28/2014 
04/28/2016 

09/10/2015 
07/13/2014 

08/31/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2014 

12/30/2014 
04/28/2016 

04/28/2016 
09/30/2015 

02/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1 1

Bond Funding Cost
Adopted:
$67,107
Current Approved:
$67,107
Actual Expenditures:
$67,107

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31