Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Metrolink Parking Lot Expansion |
Description: Addition of 230 parking spaces to the existing parking lot in the city of Rialto.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | San Bernardino |
Zip Code | 92410 |
Senate District |
32 |
Assembly District | 47 |
Congressional District | |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 3 | |
Reduced Emissions | 3 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
CASEY DAILEY | (909) 884-8276 | CDAILEY@SANBAG.CA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$1,500 | $-585 | $915 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,285 | $-1,288 | $2,997 | ||||
Local** |
$0 | $169 | $169 | ||||
Total**** | $5,785 | $-1,704 | $4,081 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$635 | $-385 | $250 | $250 | $250 | $0 | |
Right of Way |
$2,625 | $-2,625 | $0 | $0 | $0 | $0 | |
Construction |
$2,525 | $1,306 | $3,831 | $3,831 | $3,831 | $0 | |
Total* | $5,785 | $-1,704 | $4,081 | $4,081 | $4,081 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
11/30/2017 |
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2014 06/30/2014 |
|
07/31/2018 08/30/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
05/01/2014 06/01/2014 |
09/03/2019 09/03/2019 |
05/01/2020 06/30/2020 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 3 | |
Reduced Emissions | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,500,000 |
Current Approved: |
$914,919 |
Actual Expenditures: |
$914,919 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31