Caltrans Logo

Metrolink Parking Lot Expansion

Description: Addition of 230 parking spaces to the existing parking lot in the city of Rialto.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92410
 
Senate District
32
Assembly District 47
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3      
Reduced Emissions  3      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CASEY DAILEY (909) 884-8276   CDAILEY@SANBAG.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,500 $-585 $915
Non-bond Funding
State/Federal*
$4,285 $-1,288 $2,997
Local**
$0 $169 $169
 
Total**** $5,785 $-1,704 $4,081

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$635 $-385 $250 $250 $250 $0
Right of Way
$2,625 $-2,625 $0 $0 $0 $0
Construction
$2,525 $1,306 $3,831 $3,831 $3,831 $0
 
Total* $5,785 $-1,704 $4,081 $4,081 $4,081 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

11/30/2017 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
01/30/2014 

06/30/2014 
 

 
07/31/2018 

08/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2014 

06/01/2014 
09/03/2019 

09/03/2019 
05/01/2020 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3
Reduced Emissions 3

Bond Funding Cost
Adopted:
$1,500,000
Current Approved:
$914,919
Actual Expenditures:
$914,919

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31