Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Stop Improvement |
|
Description: Implement bus stop improvements throughout route bringing up to ADA compliance.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Fresno |
| City | Fresno |
| Zip Code | 93706 |
| Senate District |
31 |
| Assembly District | 14 |
| Congressional District | 20 |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 15 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
KENNETH HAMM | (559) 621-1469 | DARLENE_CHRISTINSEN@FRESNO.GOV |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $105 | $105 | ||||
| PTMISEA-99313 |
$525 | $179 | $704 | ||||
| PTMISEA-99314 |
$31 | $102 | $133 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$122 | $834 | $956 | ||||
| Local** |
$0 | $89 | $89 | ||||
| Total**** | $678 | $1,310 | $1,988 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$678 | $1,310 | $1,988 | $1,988 | $1,988 | $0 | |
| Total* | $678 | $1,310 | $1,988 | $1,988 | $1,988 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
10/21/2014 05/01/2015 |
02/01/2014 03/31/2015 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
03/01/2012 06/01/2012 |
05/07/2020 02/24/2021 |
01/01/2020 06/30/2021 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
08/01/2012 10/01/2012 |
02/24/2021 02/28/2023 |
10/31/2021 09/30/2022 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 15 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$556,000 |
| Current Approved: |
$837,400 |
| Actual Expenditures: |
$837,400 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
