Caltrans Logo

Purchase a Replacement Bus

Description: Purchase a CNG 40', 40 seated passenger and 2 wheelchair positions to replace a 2008 New Flyer Hybrid bus.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Montebello
Zip Code 90640
 
Senate District
32
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  10    10  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TOM BARRIO (323) 558-1625   TBARRIO@CITYOFMONTEBELLO.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $10 $10
PTMISEA-99314
$0 $120 $120
Non-bond Funding
State/Federal*
$0 $554 $554
Local**
$0 $9 $9
 
Total**** $0 $693 $693

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $693 $693 $693 $693 $0
 
Total* $0 $693 $693 $693 $693 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/27/2018 

09/27/2018 
 

 
09/27/2018 

09/27/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/30/2020 

06/30/2020 
04/01/2021 

04/01/2021 
01/01/2021 

03/01/2021 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 10 10
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$0
Current Approved:
$120,000
Actual Expenditures:
$120,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31