BlueGO Transit System Modernization Improvement |
|
Description: Modernization of the equipment used in the maintenance of the BlueGO transit fleet, including upgrades to BlueGO transit fleet structure & modernization of an alternative fueling station.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
El Dorado |
| City | Stateline |
| Zip Code | 89449 |
| Senate District |
04 |
| Assembly District | 01 |
| Congressional District | 04 |
| Caltrans District |
03 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | 5 |
| Increased Ridership | 5 | 5 |
| Reduced Emissions | 5 | 5 |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
NICK HAVEN | (775) 589-5256 | NHAVEN@TRPA.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $0 | $0 | ||||
| PTMISEA-99313 |
$888 | $-606 | $282 | ||||
| PTMISEA-99314 |
$112 | $-112 | $0 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $41 | $41 | ||||
| Local** |
$0 | $0 | $0 | ||||
| Total**** | $1,000 | $-676 | $324 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,000 | $-676 | $324 | $324 | $324 | $0 | |
| Total* | $1,000 | $-676 | $324 | $324 | $324 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
08/27/2014 08/27/2014 |
11/01/2015 08/31/2016 |
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
08/12/2015 08/12/2015 |
11/01/2016 01/01/2017 |
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
09/01/2012 06/30/2013 |
05/07/2019 09/27/2019 |
12/20/2018 02/29/2020 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2013 09/30/2013 |
09/05/2020 09/05/2020 |
09/01/2020 12/31/2020 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | 5 |
| Increased Ridership | 5 | 5 |
| Reduced Emissions | 5 | 5 |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$1,000,000 |
| Current Approved: |
$282,414 |
| Actual Expenditures: |
$282,414 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31