Placentia Avenue Grade Separation |
|
Description: Placentia Avenue Grade Separation between Crother Ave and Fender Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Orange |
| City | Orange |
| Zip Code | 92863 |
| Senate District |
29 |
| Assembly District | 55, 65 |
| Congressional District | 40 |
| Caltrans District |
12 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 10 | |
| Reduced Emissions | 20 | |
| Reduced Operating/Maintenance Cost | 5 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
JOE TOOLSON | (714) 560-5406 | JTOOLSON@OCTA.NET |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$642 | $4,546 | $5,188 | ||||
| PTMISEA-99314 |
$11,358 | $1,252 | $12,609 | ||||
| Non-bond Funding | |||||||
| Local** |
$55,284 | $0 | $55,284 | ||||
| Total**** | $67,284 | $5,798 | $73,082 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$4,328 | $0 | $4,328 | $4,328 | $4,328 | $0 | |
| Right of Way |
$19,410 | $0 | $19,410 | $19,410 | $19,410 | $0 | |
| Construction |
$43,546 | $5,798 | $49,344 | $49,344 | $49,344 | $0 | |
| Total* | $67,284 | $5,798 | $73,082 | $73,082 | $73,082 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2001 05/15/2001 |
|
05/01/2001 05/15/2001 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/29/2009 06/30/2010 |
|
01/29/2009 06/30/2010 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/09/2009 03/16/2011 |
|
09/09/2009 03/16/2011 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/25/2011 07/01/2014 |
09/17/2013 |
07/25/2011 11/01/2014 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2014 07/01/2017 |
09/17/2013 09/04/2014 |
11/01/2014 11/01/2014 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 10 | |
| Reduced Emissions | 20 | |
| Reduced Operating/Maintenance Cost | 5 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$12,000,000 |
| Current Approved: |
$17,797,758 |
| Actual Expenditures: |
$17,797,758 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31