Replacement of Advanced Communications System |
|
Description: Replace aging communications and computer aided dispatch and automated vehicle location mobile equipment
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Mateo |
| City | San Carlos |
| Zip Code | 94070 |
| Senate District |
08, 11 |
| Assembly District | 12, 19, 21 |
| Congressional District | 12, 14 |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 100 | 100 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
REBECCA ARTHUR | (650) 508-6368 | ARTHURR@SAMTRANS.COM |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$2,485 | $-554 | $1,931 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$8,215 | $1,833 | $10,047 | ||||
| Local** |
$0 | $101 | $101 | ||||
| Total**** | $10,700 | $1,379 | $12,079 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$850 | $0 | $850 | $850 | $850 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$9,850 | $1,379 | $11,229 | $11,229 | $11,229 | $0 | |
| Total* | $10,700 | $1,379 | $12,079 | $12,079 | $12,079 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2011 06/30/2012 |
08/20/2013 08/20/2013 |
02/01/2011 08/30/2012 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2013 09/30/2013 |
08/20/2013 03/01/2016 |
06/30/2013 06/30/2016 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2013 12/31/2013 |
03/01/2016 08/31/2017 |
07/01/2016 06/30/2017 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 100 | 100 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$2,485,333 |
| Current Approved: |
$1,930,963 |
| Actual Expenditures: |
$1,930,963 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31