- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County | Kern | 
| City | Wasco | 
| Zip Code | 93280 | 
| Senate District | 16 | 
| Assembly District | 30 | 
| Congressional District | 20 | 
| Caltrans District | 06 | 
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 5 | 5 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | BRUCE FOLTZ | (661) 758-7237 | BRFOLTZ@CI.WASCO.CA.US | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | |||||
| Bond Funding | |||||||
| PTMISEA-Interest | $0 | $0 | $0 | ||||
| PTMISEA-99313 | $10 | $0 | $10 | ||||
| PTMISEA-99314 | $7 | $0 | $7 | ||||
| Non-bond Funding | |||||||
| Local** | $0 | $0 | $0 | ||||
| Total**** | $17 | $0 | $17 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | Cost to Date** (06/30/2025 d | Cost Forecast (06/30/2025 e | Cost Variance f=c-e | ||
| Environmental | $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | $0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way | $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | $17 | $0 | $17 | $17 | $17 | $0 | |
| Total* | $17 | $0 | $17 | $17 | $17 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a | Approved Changes (mm/dd/yyyy) b | Current Approved (06/30/2025) c | % Complete (06/30/2025) d | Schedule Forecast (06/30/2025) e | Schedule Variance (months) f=c-e | 
| Begin Environmental Phase End Environmental Phase |  |  |  | 0 |  | 0 0 | 
| Begin Design (PS&E) Phase End Design (PS&E) Phase |  |  |  | 0 |  | 0 0 | 
| Begin Right of Way Phase End Right of Way Phase |  |  |  | 0 |  | 0 0 | 
| Begin Construction Phase End Construction Phase | 10/01/2013 10/31/2013 | 08/13/2015 08/13/2015 | 04/01/2016 04/30/2016 | 100 |  | 0 0 | 
| Begin Closeout Phase End Closeout Phase | 12/01/2013 12/31/2013 | 08/13/2015 08/13/2015 | 06/01/2016 06/30/2016 | 100 |  | 0 0 | 
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 5 | 5 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | $16,881 | 
| Current Approved: | $17,044 | 
| Actual Expenditures: | $17,044 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31