Bond Accountability
Rolling Stock Procurement and Security Cameras |
|
Description: Purchase of XHG CNG bus and install security cameras.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Riverside |
| City | Beaumont |
| Zip Code | 92223 |
| Senate District |
23 |
| Assembly District | 42 |
| Congressional District | |
| Caltrans District |
08 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 40 | |
| Increased Ridership | 20 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
KELSEY DE FORGE | (951) 769-8520 X337 | KELSEYD@BEAUMONTHCARES.COM |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $2 | $2 | ||||
| PTMISEA-99313 |
$441 | $0 | $441 | ||||
| PTMISEA-99314 |
$18 | $0 | $18 | ||||
| Non-bond Funding | |||||||
| Total**** | $459 | $2 | $461 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$459 | $2 | $461 | $461 | $461 | $0 | |
| Total* | $459 | $2 | $461 | $461 | $461 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2013 08/01/2013 |
07/14/2015 03/06/2016 |
11/05/2014 12/31/2015 |
75 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2013 12/01/2013 |
03/06/2016 03/06/2016 |
07/01/2016 08/01/2016 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 40 | |
| Increased Ridership | 20 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$459,151 |
| Current Approved: |
$459,151 |
| Actual Expenditures: |
$459,151 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31