| Regional Bus Replacement (2) | 
| Description: Purchase of two replacement CNG buses. | 
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County | San Bernardino | 
| City | Hesperia | 
| Zip Code | 92345 | 
| Senate District | 21 | 
| Assembly District | 33 | 
| Congressional District | |
| Caltrans District | 08 | 
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 5 | 5 | 
| Increased Ridership | 2 | 2 | 
| Reduced Emissions | 3 | 3 | 
| Reduced Operating/Maintenance Cost | 5 | 5 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | KEVIN KANE | (760) 948-4330 | KKANE@VVTA.ORG | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | |||||
| Bond Funding | |||||||
| PTMISEA-Interest | $0 | $4 | $4 | ||||
| PTMISEA-99313 | $970 | $0 | $970 | ||||
| Non-bond Funding | |||||||
| Total**** | $970 | $4 | $974 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | Cost to Date** (06/30/2025 d | Cost Forecast (06/30/2025 e | Cost Variance f=c-e | ||
| Environmental | $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | $0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way | $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | $970 | $4 | $974 | $974 | $974 | $0 | |
| Total* | $970 | $4 | $974 | $974 | $974 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a | Approved Changes (mm/dd/yyyy) b | Current Approved (06/30/2025) c | % Complete (06/30/2025) d | Schedule Forecast (06/30/2025) e | Schedule Variance (months) f=c-e | 
| Begin Environmental Phase End Environmental Phase |  |  |  | 0 |  | 0 0 | 
| Begin Design (PS&E) Phase End Design (PS&E) Phase |  |  |  | 0 |  | 0 0 | 
| Begin Right of Way Phase End Right of Way Phase |  |  |  | 0 |  | 0 0 | 
| Begin Construction Phase End Construction Phase | 03/31/2014 07/31/2014 | 03/23/2015 03/23/2015 | 11/15/2013 01/14/2014 | 100 |  | 0 0 | 
| Begin Closeout Phase End Closeout Phase | 12/31/2014 03/15/2015 | 03/23/2015 03/23/2015 | 10/17/2014 10/31/2014 | 0 |  | 0 0 | 
                                ????????
                            
                            
                            
                        No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 5 | 5 | 
| Increased Ridership | 2 | 2 | 
| Reduced Emissions | 3 | 3 | 
| Reduced Operating/Maintenance Cost | 5 | 5 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | $970,000 | 
| Current Approved: | $970,000 | 
| Actual Expenditures: | $970,000 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31