| Project Location | |
|---|---|
| County | Santa Barbara | 
| City | Santa Barbara | 
| Zip Code | 93110 | 
| Senate District | 19 | 
| Assembly District | 35 | 
| Congressional District | |
| Caltrans District | 05 | 
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 5 | 5 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | STEPHEN VANDENBURGH | (805) 961-8900 | SVANDENBURGH@SBCAG.ORG | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | |||||
| Bond Funding | |||||||
| PTMISEA-99313 | $5 | $0 | $5 | ||||
| Non-bond Funding | |||||||
| Total**** | $5 | $0 | $5 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a | Approved Changes (06/30/2025 b=c-a | Current Approved (06/30/2025 c | Cost to Date** (06/30/2025 d | Cost Forecast (06/30/2025 e | Cost Variance f=c-e | ||
| Environmental | $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | $0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way | $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | $5 | $0 | $5 | $0 | $0 | $5 | |
| Total* | $5 | $0 | $5 | $0 | $0 | $5 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a | Approved Changes (mm/dd/yyyy) b | Current Approved (06/30/2025) c | % Complete (06/30/2025) d | Schedule Forecast (06/30/2025) e | Schedule Variance (months) f=c-e | 
| Begin Environmental Phase End Environmental Phase |  |  |  | 0 |  | 0 0 | 
| Begin Design (PS&E) Phase End Design (PS&E) Phase | 07/01/2013 08/01/2013 | 09/09/2014 09/09/2014 | 12/01/2013 12/31/2013 | 0 |  | 0 0 | 
| Begin Right of Way Phase End Right of Way Phase |  |  |  | 0 |  | 0 0 | 
| Begin Construction Phase End Construction Phase | 09/01/2013 10/01/2013 | 09/09/2014 09/09/2014 | 04/01/2014 06/01/2014 | 100 |  | 0 0 | 
| Begin Closeout Phase End Closeout Phase | 11/01/2013 11/30/2013 | 09/09/2014 09/09/2014 | 07/01/2014 08/01/2014 | 100 |  | 0 0 | 
                                ????????
                            
                            
                            
                        No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 5 | 5 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | $5,000 | 
| Current Approved: | $5,000 | 
| Actual Expenditures: | $5,000 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31