                            Emergency Generator | 
                    
| 
                            Description: Purchase a back-up generatorat the Maint & Op building to address safety and functionality during power outages. This will prevent damaged equipment, ruined goods, lost revenue and diminished safety.
                             | 
                    
- Project Information
 - Contacts
 - Cost by Fund Source
 - Cost by Component
 - Schedule
 - Map
 - Closeout Info
 
| Project Location | |
|---|---|
| County | 
                                    Santa Barbara | 
| City | Santa Maria | 
| Zip Code | 93458 | 
| Senate District | 
                                    19 | 
                                
| Assembly District | 35 | 
| Congressional District | 24 | 
| Caltrans District | 
                                    05 | 
                                
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 100 | 100 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | 
                                    
                                    
                                        
                                            AUSTIN O'DELL | (805) 925-0951 | AODELL@SANTAMARIA.ORG | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                |||||
| Bond Funding | |||||||
| PTMISEA-Interest | 
                                            $10 | $7 | $17 | ||||
| PTMISEA-99313 | 
                                            $80 | $-17 | $63 | ||||
| Non-bond Funding | |||||||
| Total**** | $90 | $-10 | $80 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                    Cost to Date** (06/30/2025 d  | 
                                    
                                        
                                            Cost Forecast (06/30/2025 e  | 
                                            Cost Variance f=c-e  | 
                                        
                                    
                                ||
| Environmental | 
                                        $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | 
                                        $0 | $0 | $0 | $5 | $5 | $-5 | |
| Right of Way | 
                                    $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | 
                                    $90 | $-10 | $80 | $75 | $75 | $5 | |
| Total* | $90 | $-10 | $80 | $80 | $80 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a  | 
                                    Approved Changes (mm/dd/yyyy) b  | 
                                    Current Approved (06/30/2025) c  | 
                                    % Complete (06/30/2025) d  | 
                                    Schedule Forecast (06/30/2025) e  | 
                                    Schedule Variance (months) f=c-e  | 
                                
| 
                                        
                                            Begin Environmental Phase
                                             End Environmental Phase  | 
                                      | 
                                      | 
                                      | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Design (PS&E) Phase
                                         End Design (PS&E) Phase  | 
                                    05/01/2017  07/01/2017  | 
                                      | 
                                    05/01/2017  07/01/2017  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Right of Way Phase
                                         End Right of Way Phase  | 
                                    07/01/2017  08/01/2017  | 
                                      | 
                                    07/01/2017  08/01/2017  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Construction Phase
                                         End Construction Phase  | 
                                    08/30/2017  09/30/2017  | 
                                    04/30/2019  04/17/2020  | 
                                    02/15/2019  10/30/2019  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Closeout Phase
                                         End Closeout Phase  | 
                                    01/01/2018  02/28/2018  | 
                                    08/28/2020  08/28/2020  | 
                                    07/15/2020  08/10/2020  | 
                                    100 |   | 
                                    0  0  | 
                                
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 100 | 100 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | 
                                    $89,588 | 
| Current Approved: | 
                                    $62,893 | 
| Actual Expenditures: | 
                                    $62,893 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31