Description: In and near Stockton from south of Route 205 to north of Route 12; also on Route 205 (PM 0.0/13.4). Install traffic monitoring stations. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95203 |
Senate District |
05 |
Assembly District | 26 |
Congressional District | 03 |
Caltrans District |
10 |
County/State Route | San Joaquin 5 |
Postmile Begin/End | 10.8 41.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 87 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Construction Phase |
Department of Transportation | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$2,260 | $319 | $2,579 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $2,260 | $319 | $2,579 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$141 | $0 | $141 | $82 | |||
Design(PS&E) |
$205 | $0 | $205 | $80 | |||
Right of Way |
$2 | $0 | $2 | $0 | |||
Construction |
$1,912 | $319 | $2,231 | $1,693 | |||
Total* | $2,260 | $319 | $2,579 | $1,856 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 08/01/2007 |
|
07/01/2007 08/01/2007 |
100 | 07/24/2007 08/21/2007 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 08/01/2007 |
|
07/01/2007 08/01/2007 |
100 | 08/21/2007 09/20/2007 |
-2 -2 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2007 08/01/2007 |
|
07/01/2007 08/01/2007 |
100 | 07/01/2007 10/09/2007 |
0 -2 |
Begin Construction Phase
End Construction Phase |
10/01/2007 06/01/2008 |
|
10/01/2007 06/01/2008 |
100 | 11/09/2007 06/30/2008 |
-1 -1 |
Begin Closeout Phase
End Closeout Phase |
06/30/2008 07/01/2009 |
06/07/2007 06/07/2007 |
06/30/2008 07/01/2009 |
100 | 06/30/2008 12/07/2009 |
0 -5 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 87 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,260,000 |
Current Approved: |
$1,573,000 |
Actual Expenditures: |
$1,519,427 |
Status as of December 31, 2023.