Install Vehicle Detection Stations (VDS)

Description: In and near Stockton from south of Route 205 to north of Route 12; also on Route 205 (PM 0.0/13.4). Install traffic monitoring stations. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95203
 
Senate District
05
Assembly District 26
Congressional District 03
 
Caltrans District
10
 
 
County/State Route San Joaquin 5
Postmile Begin/End 10.8 41.9
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  87      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Right of Way Phase
Department of Transportation Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Construction Phase
Department of Transportation Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$2,260 $319 $2,579
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $2,260 $319 $2,579

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$141 $0 $141 $82
Design(PS&E)
$205 $0 $205 $80
Right of Way
$2 $0 $2 $0
Construction
$1,912 $319 $2,231 $1,693
 
Total* $2,260 $319 $2,579 $1,856

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

08/01/2007 
 

 
07/01/2007 

08/01/2007 
100  07/24/2007 

08/21/2007 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

08/01/2007 
 

 
07/01/2007 

08/01/2007 
100  08/21/2007 

09/20/2007 
-2 

-2 
Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

08/01/2007 
 

 
07/01/2007 

08/01/2007 
100  07/01/2007 

10/09/2007 


-2 
Begin Construction Phase

End Construction Phase
10/01/2007 

06/01/2008 
 

 
10/01/2007 

06/01/2008 
100  11/09/2007 

06/30/2008 
-1 

-1 
Begin Closeout Phase

End Closeout Phase
06/30/2008 

07/01/2009 
06/07/2007 

06/07/2007 
06/30/2008 

07/01/2009 
100  06/30/2008 

12/07/2009 


-5 
????????
Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 87

Bond Funding Cost
Adopted:
$2,260,000
Current Approved:
$1,573,000
Actual Expenditures:
$1,519,427

 

Status as of December 31, 2023.