Caltrans Logo

Purchase Service Vehicle

Description: Acquire a pickup truck for minor on-call bus maintenance out on the road instead of having bus towed back to maintenance facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Calaveras
City San Andreas
Zip Code 95249
 
Senate District
01
Assembly District 25
Congressional District 04
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  1    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MELISSA EADS (209) 754-2094   MEADS@CALACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$32 $5 $37
Non-bond Funding
 
Total**** $32 $6 $38

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$32 $6 $38 $38 $38 $0
 
Total* $32 $6 $38 $38 $38 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2015 

08/01/2015 
05/12/2016 

05/12/2016 
12/03/2015 

03/04/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/01/2015 
05/12/2016 

05/04/2017 
04/08/2016 

02/28/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 1 2

Bond Funding Cost
Adopted:
$32,000
Current Approved:
$37,302
Actual Expenditures:
$37,302

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31