Caltrans Logo

Unitrans High Capacity Transit Buses

Description: Purchase two high capacity transit buses, generally 80-passenger buses similar to Enviro500 buses, run on biodiesel fuel and fully accessible.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yolo
City Davis
Zip Code 95616
 
Senate District
02, 08
Assembly District 05
Congressional District 01
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Increased Ridership      2  
Reduced Emissions      5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANTHONY PALMERE (530) 754-5814   AJPALMERE@UCDAVIS.EDU
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $25 $25
PTMISEA-99314
$781 $0 $781
Non-bond Funding
Local**
$1,400 $0 $1,400
 
Total**** $2,181 $25 $2,207

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,181 $25 $2,207 $2,207 $2,207 $0
 
Total* $2,181 $25 $2,207 $2,207 $2,207 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2017 

12/01/2017 
09/19/2019 

09/19/2019 
10/01/2018 

10/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2018 

03/31/2018 
04/12/2018 

04/12/2018 
01/15/2019 

03/31/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Increased Ridership 2
Reduced Emissions 5

Bond Funding Cost
Adopted:
$781,219
Current Approved:
$781,219
Actual Expenditures:
$781,219

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31