Gold Country Stage - Transit Services Facility Improvement |
Description: Relocate and Construct a new Transit Services base operation office and bus parking/storage areas.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Nevada |
City | Nevada City |
Zip Code | 95959 |
Senate District |
03 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | 20 |
Increased Ridership | 5 | |
Reduced Emissions | 5 | |
Reduced Operating/Maintenance Cost | 10 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
SUSAN HEALY-HARMAN | (530) 477-0103 | SUSAN.HEALY-HARMAN@CO.NEVADA.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $43 | $43 | ||||
PTMISEA-99313 |
$500 | $-21 | $479 | ||||
Non-bond Funding | |||||||
Total**** | $500 | $22 | $522 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$500 | $22 | $522 | $522 | $522 | $0 | |
Total* | $500 | $22 | $522 | $522 | $522 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2015 02/01/2016 |
|
01/01/2015 02/01/2016 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2016 03/31/2017 |
|
05/01/2016 05/01/2018 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/01/2017 12/31/2018 |
08/29/2020 03/09/2021 |
05/01/2019 07/01/2020 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/01/2018 06/30/2019 |
03/09/2021 03/09/2021 |
07/01/2020 12/31/2020 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | 20 |
Increased Ridership | 5 | |
Reduced Emissions | 5 | |
Reduced Operating/Maintenance Cost | 10 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$500,000 |
Current Approved: |
$478,895 |
Actual Expenditures: |
$478,895 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31