Clean Air Express Bus Replacement

Description: Replace one Clean Air Express Coach with 45 ft diesel MCI Coach 57 seats.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93110
 
Senate District
19
Assembly District 35, 37
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
Reduced Operating/Maintenance Cost  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SCOTT SPAULDING (805) 961-8920   SSPAULDING@SBCAG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$88 $0 $88
PTMISEA-99314
$212 $0 $212
Non-bond Funding
Local**
$420 $0 $420
 
Total**** $720 $0 $720

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$720 $0 $720 $720 $720 $0
 
Total* $720 $0 $720 $720 $720 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2018 

09/01/2018 
 

 
05/01/2018 

09/01/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2019 

06/01/2019 
 

 
08/16/2019 

08/16/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1
Reduced Operating/Maintenance Cost 2 2

Bond Funding Cost
Adopted:
$300,000
Current Approved:
$300,000
Actual Expenditures:
$300,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31