Caltrans Logo

Cancelled - Grant Rea Park Terminal Rehab

Description: Rehabilitate the layover facility at Grant Rea Park, project would include repaving layover zone and installation of a self-cleaning restroom.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Montebello
Zip Code 90640
 
Senate District
32
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TOM BARRIO (323) 558-1625   TBARRIO@CITYOFMONTEBELLO.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
Non-bond Funding
 
Total**** $0 $0 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $0 $0 $0 $0 $0
 
Total* $0 $0 $0 $0 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2018 

07/01/2018 
 

 
03/01/2018 

07/01/2018 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2018 

09/01/2018 
 

 
07/01/2018 

09/01/2018 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2018 

03/01/2019 
 

 
10/01/2020 

03/01/2021 
 

 


Begin Closeout Phase

End Closeout Phase
03/01/2019 

06/30/2019 
04/02/2021 

04/02/2021 
12/01/2022 

12/31/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31