Caltrans Logo

Construction of 15 Bus Bench Shelters

Description: Purchase and install 15 bus bench shelters for the use of passengers of the transit system

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
18
Assembly District 32
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BETTY DENNISON (661) 862-8616   BETTY DENNISON
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$0 $25 $25
PTMISEA-99314
$153 $-88 $64
Non-bond Funding
State/Federal*
$0 $22 $22
 
Total**** $153 $-39 $114

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$153 $-39 $114 $114 $114 $0
 
Total* $153 $-39 $114 $114 $114 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
04/14/2014 

04/14/2014 
01/01/2015 

03/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

06/30/2013 
03/09/2015 

03/09/2015 
03/01/2015 

06/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2013 

08/31/2013 
03/09/2015 

03/09/2015 
12/01/2015 

12/31/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3

Bond Funding Cost
Adopted:
$152,777
Current Approved:
$89,889
Actual Expenditures:
$89,889

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31