Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Rehabilitation Program (FY11) |
Description: Rehabilitation of up to 314 buses of LACMTA's fleet.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 32 |
Assembly District | 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 17 | 17 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
NELA DE CASTRO | (213) 922-6166 | DECASTROM@METRO.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $457 | $457 | ||||
PTMISEA-99313 |
$0 | $3,932 | $3,932 | ||||
PTMISEA-99314 |
$15,000 | $33,588 | $48,588 | ||||
Non-bond Funding | |||||||
Total**** | $15,000 | $37,976 | $52,976 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$15,000 | $37,976 | $52,976 | $52,976 | $52,976 | $0 | |
Total* | $15,000 | $37,976 | $52,976 | $52,976 | $52,976 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2011 10/01/2013 |
06/13/2014 |
07/01/2011 02/01/2014 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2013 12/01/2013 |
06/13/2014 06/13/2014 |
03/01/2014 05/01/2014 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 17 | 17 |
Bond Funding Cost | |
---|---|
Adopted: |
$15,000,000 |
Current Approved: |
$52,519,619 |
Actual Expenditures: |
$52,519,619 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31