Caltrans Logo

Bus Rehabilitation Program (FY11)

Description: Rehabilitation of up to 314 buses of LACMTA's fleet.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 32
Assembly District 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  17    17  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
NELA DE CASTRO (213) 922-6166   DECASTROM@METRO.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $457 $457
PTMISEA-99313
$0 $3,932 $3,932
PTMISEA-99314
$15,000 $33,588 $48,588
Non-bond Funding
 
Total**** $15,000 $37,976 $52,976

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$15,000 $37,976 $52,976 $52,976 $52,976 $0
 
Total* $15,000 $37,976 $52,976 $52,976 $52,976 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2011 

10/01/2013 
 

06/13/2014 
07/01/2011 

02/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/01/2013 
06/13/2014 

06/13/2014 
03/01/2014 

05/01/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 17 17

Bond Funding Cost
Adopted:
$15,000,000
Current Approved:
$52,519,619
Actual Expenditures:
$52,519,619

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31