Regional Transit Center

Description: Development and construction of a Regional Transit Center in Torrance.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Torrance
Zip Code 90503
 
Senate District
28
Assembly District 53
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    5  
Increased Ridership  15    7  
Reduced Emissions  20      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JIM MILLS (310) 618-6291   JMILLS@TORRNET.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $281 $281
PTMISEA-99314
$2,500 $484 $2,984
Non-bond Funding
State/Federal*
$0 $243 $243
Local**
$19,000 $7,700 $26,700
 
Total**** $21,500 $8,707 $30,207

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$21,500 $8,707 $30,207 $30,207 $30,207 $0
 
Total* $21,500 $8,707 $30,207 $30,207 $30,207 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2012 

07/01/2014 
10/16/2015 

04/15/2019 
08/01/2015 

06/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
 

07/01/2014 
 

12/08/2023 
 

06/01/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 5
Increased Ridership 15 7
Reduced Emissions 20
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$2,500,000
Current Approved:
$2,983,670
Actual Expenditures:
$2,983,670

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31