ACE Maintenance and Layover Facility

Description: Construct 64 acre facility to be used for repair, maintenance, cleaning, and overnight storage of the train sets used in the ACE service and future rail service expansions.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
15, 18
Assembly District 09, 10
Congressional District 10, 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  4      
Reduced Operating/Maintenance Cost  4      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT TODD (510) 208-7420   MTODD@ALAMEDACTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$708 $79 $787
Non-bond Funding
State/Federal*
$21,622 $7,561 $29,183
Local**
$53,970 $-4,705 $49,265
 
Total**** $76,300 $2,935 $79,235

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,112 $0 $2,112 $2,112 $2,112 $0
Right of Way
$9,400 $0 $9,400 $9,400 $9,400 $0
Construction
$64,788 $2,935 $67,723 $67,723 $67,723 $0
 
Total* $76,300 $2,935 $79,235 $79,235 $79,235 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

12/31/2008 
 

 
01/01/2001 

12/31/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2001 

01/31/2011 
 

 
12/31/2008 

01/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
05/01/2008 

12/31/2008 
 

 
05/01/2008 

12/31/2008 
100   

 


Begin Construction Phase

End Construction Phase
06/01/2011 

12/31/2013 
 

03/07/2016 
08/01/2011 

12/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

03/31/2014 
03/07/2016 

03/07/2016 
06/30/2015 

12/31/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 4
Reduced Operating/Maintenance Cost 4

Bond Funding Cost
Adopted:
$707,887
Current Approved:
$787,116
Actual Expenditures:
$787,116

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31