Placer County Bus Stop Improvements

Description: To enhance and improve passenger safety and comfort while at Placer County bus stops. Improvements include shelter, lighting, pedestrian access, seating and signage.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILL GARNER (530) 745-7582   WGARNER@PLACER.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $38 $38
PTMISEA-99313
$163 $0 $163
PTMISEA-99314
$0 $9 $9
Non-bond Funding
 
Total**** $163 $47 $211

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$30 $0 $30 $0 $0 $30
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$133 $47 $181 $211 $211 $-30
 
Total* $163 $47 $211 $211 $211 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2011 

02/01/2012 
 

 
12/01/2011 

02/01/2012 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2012 

06/01/2012 
 

 
04/01/2012 

06/01/2012 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/15/2012 

11/15/2012 
10/25/2013 

05/10/2016 
11/01/2013 

10/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2012 

01/01/2013 
09/02/2016 

04/25/2019 
12/31/2017 

03/31/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 3

Bond Funding Cost
Adopted:
$163,399
Current Approved:
$172,070
Actual Expenditures:
$172,070

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31