Plumas County Bus-Purchase Replacement Bus

Description: Applying for funding for bus replacements. Plumas Transit System is in need of one diesel Type 7, medium duty bus with 30-passenger capacity.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Plumas
City Quincy
Zip Code 95971
 
Senate District
03
Assembly District 01
Congressional District 04
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100    14  
Increased Ridership  2      
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  10    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOHN MANNLE (530) 283-6498   JOHNMANNLE@COUNTYOFPLUMAS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$130 $-2 $128
Non-bond Funding
Local**
$0 $1 $1
 
Total**** $130 $-1 $129

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$130 $-1 $129 $129 $129 $0
 
Total* $130 $-1 $129 $129 $129 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2012 

12/15/2012 
10/21/2014 

10/21/2014 
11/19/2012 

08/16/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
01/15/2013 

02/15/2013 
10/21/2014 

10/21/2014 
09/19/2013 

02/14/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100 14
Increased Ridership 2
Reduced Emissions 10
Reduced Operating/Maintenance Cost 10 3

Bond Funding Cost
Adopted:
$130,000
Current Approved:
$128,049
Actual Expenditures:
$128,049

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31