Transit Fare Collection System (PHASE I)

Description: Purchasing and installing fare collection equipment at the Lodi Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Lodi
Zip Code 95240
 
Senate District
14
Assembly District 10
Congressional District 10
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30      
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PAULA FERNANDEZ (209) 333-6800   PFERNANDEZ@LODI.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$150 $-105 $45
Non-bond Funding
 
Total**** $150 $-105 $45

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$150 $-105 $45 $45 $45 $0
 
Total* $150 $-105 $45 $45 $45 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2011 

10/31/2011 
 

 
07/01/2011 

10/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2012 

10/31/2012 
02/26/2014 

02/26/2014 
12/01/2013 

12/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2012 

12/31/2012 
02/26/2014 

02/26/2014 
03/01/2015 

03/31/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Increased Ridership 5

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$45,000
Actual Expenditures:
$45,000

Click to view the Semi-Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31