Caltrans Logo

Hammer Triangle Transfer Station

Description: Construct transfer station to be located at the intersections of Hammer Lane, Lower Sacramento Road, & Thorton Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
15, 17, 26
Assembly District 05, 14
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  5    11  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566   DDEMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$800 $-53 $747
Non-bond Funding
Local**
$800 $0 $800
 
Total**** $1,600 $-53 $1,547

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$800 $0 $800 $800 $800 $0
Construction
$800 $-53 $747 $747 $747 $0
 
Total* $1,600 $-53 $1,547 $1,547 $1,547 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2011 

12/31/2011 
 

 
07/01/2011 

12/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/01/2011 

12/31/2011 
 

 
07/01/2011 

12/31/2011 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2011 

12/31/2011 
 

 
07/01/2011 

12/31/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2012 

03/01/2012 
03/19/2014 

03/19/2014 
01/01/2014 

02/21/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 5 11

Bond Funding Cost
Adopted:
$800,000
Current Approved:
$747,421
Actual Expenditures:
$747,421

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31