Passenger Information System and CNG buses

Description: Purchase computer automated dispatch system, AVL and real time passenger information system, and purchase of 3 CNG buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
34
Assembly District 18
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 782-7448   RTREE@CI_PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$227 $0 $227
PTMISEA-99314
$16 $0 $16
Non-bond Funding
State/Federal*
$500 $-380 $120
Local**
$82 $-73 $9
 
Total**** $825 $-452 $373

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$825 $-452 $373 $373 $373 $0
 
Total* $825 $-452 $373 $373 $373 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2012 

04/01/2014 
08/12/2014 

08/12/2014 
08/01/2012 

07/10/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2014 

05/01/2014 
08/12/2014 

08/12/2014 
07/22/2013 

08/08/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15 25

Bond Funding Cost
Adopted:
$243,000
Current Approved:
$243,000
Actual Expenditures:
$243,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31