Bus Stop Improvement

Description: Implement bus stop improvements throughout route bringing up to ADA compliance.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93706
 
Senate District
31
Assembly District 14
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KENNETH HAMM (559) 621-1469   DARLENE_CHRISTINSEN@FRESNO.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $105 $105
PTMISEA-99313
$525 $179 $704
PTMISEA-99314
$31 $102 $133
Non-bond Funding
State/Federal*
$122 $834 $956
Local**
$0 $89 $89
 
Total**** $678 $1,310 $1,988

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$678 $1,310 $1,988 $1,988 $1,988 $0
 
Total* $678 $1,310 $1,988 $1,988 $1,988 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
10/21/2014 

05/01/2015 
02/01/2014 

03/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

06/01/2012 
05/07/2020 

02/24/2021 
01/01/2020 

06/30/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2012 

10/01/2012 
02/24/2021 

02/28/2023 
10/31/2021 

09/30/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15

Bond Funding Cost
Adopted:
$556,000
Current Approved:
$837,400
Actual Expenditures:
$837,400

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31