Downtown Circulator

Description: Purchase two electricbuses and charging startion infrastructure for a circulator route in downtown Fresno

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93706
 
Senate District
31
Assembly District 14
Congressional District 14
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KENNETH HAMM (559) 621-1469   DARLENE_CHRISTINSEN@FRESNO.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$388 $0 $388
PTMISEA-99314
$138 $0 $138
Non-bond Funding
State/Federal*
$12,859 $-2,141 $10,718
Local**
$0 $1 $1
 
Total**** $13,385 $-2,140 $11,245

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13,385 $-2,140 $11,245 $11,245 $11,245 $0
 
Total* $13,385 $-2,140 $11,245 $11,245 $11,245 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2011 

01/01/2012 
 

 
08/01/2011 

01/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2012 

07/31/2012 
03/23/2016 

02/28/2023 
01/01/2015 

03/31/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2012 

11/30/2012 
02/28/2023 

02/28/2023 
01/01/2023 

01/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 10

Bond Funding Cost
Adopted:
$526,000
Current Approved:
$526,000
Actual Expenditures:
$526,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31