Bus Wash Facility Upgrade

Description: Replace all systems and sub-systems of bus wash facility with new, lower cost, higher efficiency systems.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Montebello
Zip Code 90640
 
Senate District
30
Assembly District 58
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    20  
Reduced Operating/Maintenance Cost  50    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GLORIA GALLARDO (323) 887-4609   GGALLARDO@CITYOFMONTEBELLO.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99314
$60 $352 $412
Non-bond Funding
State/Federal*
$400 $0 $400
Local**
$40 $-40 $0
 
Total**** $500 $315 $815

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$500 $315 $815 $815 $815 $0
 
Total* $500 $315 $815 $815 $815 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

12/31/2012 
 

03/20/2014 
11/01/2012 

06/30/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2013 

11/30/2013 
11/09/2017 

12/23/2022 
10/31/2017 

06/30/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2013 

02/01/2014 
04/01/2021 

12/23/2022 
12/01/2022 

12/21/2022 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 20
Reduced Operating/Maintenance Cost 50 15

Bond Funding Cost
Adopted:
$60,000
Current Approved:
$411,962
Actual Expenditures:
$411,962

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31