Madera County Park and Ride Lots

Description: Build lots to enaable travelers accesss to areas might not have otherwise

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
13
Assembly District 31
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD POYTHRESS (559) 675-0721   RICHARD@MADERACTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$834 $-1 $834
Non-bond Funding
 
Total**** $834 $5 $839

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $31 $31 $-31
Right of Way
$343 $-312 $31 $0 $0 $31
Construction
$491 $317 $808 $808 $808 $0
 
Total* $834 $5 $839 $839 $839 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
02/26/2020 

02/26/2020 
12/01/2017 

06/01/2020 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
02/26/2020 

02/26/2020 
06/01/2019 

06/01/2020 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2013 

10/01/2016 
02/26/2020 

02/26/2020 
06/01/2020 

12/01/2021 
 

 


Begin Construction Phase

End Construction Phase
03/01/2015 

09/01/2015 
02/26/2020 

08/17/2022 
03/01/2021 

04/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2015 

12/01/2015 
08/17/2022 

08/17/2022 
05/31/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 1

Bond Funding Cost
Adopted:
$834,482
Current Approved:
$833,681
Actual Expenditures:
$833,681

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31