Caltrans Logo

CATX Facility Improvements

Description: Improve facilities for Chowchilla Area Transit Express

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 31
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      5  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD POYTHRESS (559) 675-0721   RICHARD@MADERACTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$216 $35 $251
Non-bond Funding
 
Total**** $216 $35 $251

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$216 $35 $251 $251 $251 $0
 
Total* $216 $35 $251 $251 $251 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
03/11/2016 

03/11/2016 
09/01/2016 

05/01/2017 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/11/2016 

03/11/2016 
06/01/2017 

09/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2013 

10/01/2013 
03/11/2016 

03/11/2016 
09/30/2017 

03/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/01/2013 
10/28/2022 

10/28/2022 
10/01/2022 

10/31/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$215,852
Current Approved:
$250,747
Actual Expenditures:
$250,747

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31