Local Bus Stop Revitalization

Description: Bus Stop Improvements in Marin County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Marin
City San Francisco
Zip Code 94129
 
Senate District
06
Assembly District 03
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GAYLE PRIOR (415) 923-2373   GPRIOR@GOLDENGATE.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$400 $0 $400
Non-bond Funding
State/Federal*
$1,600 $0 $1,600
Local**
$0 $40 $40
 
Total**** $2,000 $40 $2,040

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,000 $40 $2,040 $2,017 $2,017 $23
 
Total* $2,000 $40 $2,040 $2,017 $2,017 $23

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2011 

06/30/2011 
08/15/2013 

02/15/2019 
07/01/2012 

02/01/2019 
90   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

08/31/2013 
08/22/2019 

08/22/2019 
09/30/2019 

10/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31