Marin County Bus Stop Improvements

Description: Bus stop improvements in Marin County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin
City San Francisco
Zip Code 94129
 
Senate District
06
Assembly District 03
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
Increased Ridership  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GAYLE PRIOR (415) 923-2373   GPRIOR@GOLDENGATE.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$985 $887 $1,872
PTMISEA-99314
$0 $150 $150
Non-bond Funding
Local**
$300 $488 $788
 
Total**** $1,285 $1,524 $2,809

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $788 $788 $788 $788 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,285 $736 $2,021 $2,021 $2,021 $0
 
Total* $1,285 $1,524 $2,809 $2,809 $2,809 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

12/30/2012 
 

 
07/01/2012 

12/30/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2013 

06/15/2013 
 

09/09/2014 
03/01/2013 

03/31/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

12/30/2013 
03/01/2017 

03/01/2017 
07/01/2016 

06/30/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

02/01/2014 
03/01/2017 

03/01/2017 
06/30/2017 

12/31/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1
Increased Ridership 1 1

Bond Funding Cost
Adopted:
$985,000
Current Approved:
$1,871,822
Actual Expenditures:
$1,871,822

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31