City of Elk Grove Rolling Stock Replace 3 buses

Description: City of Elk Grove Rolling Stock Replace 3 buse

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95814
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  7    8  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GARY TAYLOR (916) 340-6279   GTAYLOR@SACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,597 $-4 $1,593
Non-bond Funding
 
Total**** $1,597 $-4 $1,593

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,597 $-4 $1,593 $1,593 $1,593 $0
 
Total* $1,597 $-4 $1,593 $1,593 $1,593 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2012 

12/01/2301 
10/15/2013 

10/15/2013 
07/01/2013 

08/09/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2013 

06/01/2013 
10/15/2013 

10/15/2013 
04/01/2014 

06/30/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 7 8

Bond Funding Cost
Adopted:
$1,596,693
Current Approved:
$1,593,017
Actual Expenditures:
$1,593,017

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31