City of Folsom Surveillance Equipment

Description: Purchase and install new surveillance equipment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95814
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GARY TAYLOR (916) 340-6279   GTAYLOR@SACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$38 $0 $38
Non-bond Funding
 
Total**** $38 $0 $38

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$38 $0 $38 $38 $38 $0
 
Total* $38 $0 $38 $38 $38 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

12/01/2013 
09/24/2015 

09/24/2015 
03/20/2014 

12/12/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

09/01/2014 
09/24/2015 

09/24/2015 
12/13/2014 

07/20/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 2 2

Bond Funding Cost
Adopted:
$37,500
Current Approved:
$37,500
Actual Expenditures:
$37,500

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31