CNG Slow Fill Compressor

Description: Replacing the failing compressor unit in the City of Turlock's CNG Slow Fill fueling station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
25
Assembly District 12
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  7      
Reduced Emissions  1      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SCOTT MEDEIROS (209) 668-5520   SMEDEIROS@TURLOCK.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$350 $0 $350
Non-bond Funding
State/Federal*
$0 $39 $39
 
Total**** $350 $39 $389

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$350 $39 $389 $389 $389 $0
 
Total* $350 $39 $389 $389 $389 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

 
08/29/2013 

 
10/01/2012 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2012 

10/01/2012 
08/29/2013 

08/29/2013 
09/01/2013 

10/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2012 

04/01/2013 
03/10/2014 

09/04/2014 
10/25/2013 

09/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2013 

06/01/2013 
03/10/2015 

03/10/2015 
01/22/2015 

04/30/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 7
Reduced Emissions 1
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$350,000
Current Approved:
$350,000
Actual Expenditures:
$350,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31