Transit Transfer Center PHASE II

Description: Expansion of the City of Turlock's Transit Transfer Center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
25
Assembly District 12
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Increased Ridership  5    5  
Reduced Emissions      1  
Reduced Operating/Maintenance Cost  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SCOTT MEDEIROS (209) 668-5520   SMEDEIROS@TURLOCK.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $30 $30
PTMISEA-99313
$500 $550 $1,050
PTMISEA-99314
$32 $18 $50
Non-bond Funding
 
Total**** $532 $597 $1,130

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$532 $597 $1,130 $1,130 $1,130 $0
 
Total* $532 $597 $1,130 $1,130 $1,130 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2012 

12/01/2012 
08/29/2013 

08/29/2013 
09/01/2013 

12/01/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

02/01/2013 
08/29/2013 

08/29/2013 
09/01/2013 

07/01/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/01/2012 

09/01/2012 
 

 
07/01/2012 

09/01/2012 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

11/01/2013 
09/21/2017 

03/20/2019 
06/22/2017 

12/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2013 

02/01/2014 
03/20/2019 

03/09/2020 
12/01/2019 

12/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Increased Ridership 5 5
Reduced Emissions 1
Reduced Operating/Maintenance Cost 2 2

Bond Funding Cost
Adopted:
$532,437
Current Approved:
$1,099,641
Actual Expenditures:
$1,099,641

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31