Caltrans Logo

Purchase one CNG Transit Bus

Description: City of Dinuba will purchase one CNG transit bus. Bus is 24 footer with 16 passenger capacity and ADA compliance

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Visalia
Zip Code 93277
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  17    10  
Reduced Operating/Maintenance Cost  17      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CHRISTINE CHAVEZ (559) 624-7270   CHCHAVEZ@CO.TULARE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$135 $-21 $114
Non-bond Funding
 
Total**** $135 $-21 $114

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$135 $-21 $114 $114 $114 $0
 
Total* $135 $-21 $114 $114 $114 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2013 

08/01/2013 
10/09/2014 

10/09/2014 
03/21/2014 

10/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
08/15/2013 

09/15/2013 
03/19/2015 

03/19/2015 
11/15/2014 

12/15/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 17 10
Reduced Operating/Maintenance Cost 17

Bond Funding Cost
Adopted:
$135,350
Current Approved:
$114,056
Actual Expenditures:
$114,056

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31