BlueGO Transit System Modernization Improvement |
Description: Modernization of the equipment used in the maintenance of the BlueGO transit fleet, including upgrades to BlueGO transit fleet structure & modernization of an alternative fueling station.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
El Dorado |
City | Stateline |
Zip Code | 89449 |
Senate District |
04 |
Assembly District | 01 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Increased Ridership | 5 | 5 |
Reduced Emissions | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
NICK HAVEN | (775) 589-5256 | NHAVEN@TRPA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $0 | $0 | ||||
PTMISEA-99313 |
$888 | $-606 | $282 | ||||
PTMISEA-99314 |
$112 | $-112 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $41 | $41 | ||||
Local** |
$0 | $0 | $0 | ||||
Total**** | $1,000 | $-676 | $324 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,000 | $-676 | $324 | $324 | $324 | $0 | |
Total* | $1,000 | $-676 | $324 | $324 | $324 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
08/27/2014 08/27/2014 |
11/01/2015 08/31/2016 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
08/12/2015 08/12/2015 |
11/01/2016 01/01/2017 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2012 06/30/2013 |
05/07/2019 09/27/2019 |
12/20/2018 02/29/2020 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2013 09/30/2013 |
09/05/2020 09/05/2020 |
09/01/2020 12/31/2020 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Increased Ridership | 5 | 5 |
Reduced Emissions | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,000,000 |
Current Approved: |
$282,414 |
Actual Expenditures: |
$282,414 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31