Caltrans Logo

Transit Vehicle Purchase (Phase 4)

Description: Transit Vehicle Purchase (Phase 4)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Clovis, Ca
Zip Code 93612
 
Senate District
14
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Operating/Maintenance Cost      20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SHONNA HALTERMAN (559) 324-2767   SHONNAH@CITYOFCLOVIS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$237 $-171 $66
PTMISEA-99314
$23 $0 $23
Non-bond Funding
 
Total**** $259 $-169 $90

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$259 $-169 $90 $90 $90 $0
 
Total* $259 $-169 $90 $90 $90 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2012 

08/30/2012 
04/11/2014 

08/21/2014 
03/01/2014 

03/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
03/30/2013 

06/01/2013 
08/21/2014 

08/21/2014 
07/31/2014 

08/15/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Operating/Maintenance Cost 20

Bond Funding Cost
Adopted:
$259,370
Current Approved:
$88,839
Actual Expenditures:
$88,839

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31