Caltrans Logo

Low-Floor Passenger Vehicles

Description: Low-Floor Passenger Vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
29
Assembly District 14
Congressional District 18
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Operating/Maintenance Cost      15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFERY WEBSTER (559) 233-6789   JWEBSTER_RURALTRANSIT@FRESNOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$3,408 $0 $3,408
Non-bond Funding
 
Total**** $3,408 $0 $3,408

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,408 $0 $3,408 $3,408 $3,408 $0
 
Total* $3,408 $0 $3,408 $3,408 $3,408 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/30/2011 

05/31/2012 
08/04/2015 

08/04/2015 
08/30/2013 

08/06/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
07/31/2012 

08/31/2012 
08/04/2015 

08/04/2015 
01/15/2015 

02/15/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$3,408,000
Current Approved:
$3,408,000
Actual Expenditures:
$3,408,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31