Caltrans Logo

Construction of Hub Station

Description: Construction of Hub Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Kern
City Ridgecrest
Zip Code 93555
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STARLA SHAVER (760) 499-5041   SSHAVER@CI_RIDGECREST_CA_US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$186 $0 $186
Non-bond Funding
 
Total**** $186 $7 $193

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$186 $7 $193 $186 $186 $7
 
Total* $186 $7 $193 $186 $186 $7

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
03/04/2015 

03/04/2015 
05/31/2014 

11/01/2014 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/20/2012 

09/20/2012 
03/04/2015 

03/04/2015 
02/28/2015 

04/30/2015 
80   

 


Begin Right of Way Phase

End Right of Way Phase
06/20/2012 

12/20/2012 
03/04/2015 

03/04/2015 
04/30/2015 

07/30/2015 
 

 


Begin Construction Phase

End Construction Phase
12/20/2012 

06/30/2014 
09/16/2015 

09/16/2015 
01/30/2016 

01/30/2017 
 

 


Begin Closeout Phase

End Closeout Phase
06/30/2014 

07/30/2014 
08/29/2018 

08/29/2018 
08/31/2018 

10/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31