Caltrans Logo

Construction of Maintenance Facility

Description: Construction of Maintenance Facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Ridgecrest
Zip Code 93555
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STARLA SHAVER (760) 499-5041   SSHAVER@CI_RIDGECREST_CA_US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$830 $0 $830
Non-bond Funding
Local**
$0 $833 $833
 
Total**** $830 $839 $1,669

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$830 $839 $1,669 $1,669 $1,669 $0
 
Total* $830 $839 $1,669 $1,669 $1,669 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/20/2012 

06/30/2012 
03/17/2014 

03/17/2014 
08/21/2013 

12/21/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/20/2012 

06/30/2014 
09/16/2015 

03/03/2015 
10/01/2015 

12/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2014 

08/30/2014 
07/16/2019 

07/16/2019 
04/17/2017 

08/29/2017 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 25

Bond Funding Cost
Adopted:
$830,000
Current Approved:
$830,000
Actual Expenditures:
$830,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31