Auto Bus Wash System and Bus Shelter

Description: Auto Bus Wash System and Bus Shelter

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Handford
Zip Code 93232
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership      2  
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANGIE DOW (559) 852-2591   ANGIE.DOW@KINGS.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$716 $0 $716
PTMISEA-99314
$15 $0 $15
Non-bond Funding
 
Total**** $731 $0 $731

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$731 $0 $731 $731 $731 $0
 
Total* $731 $0 $731 $731 $731 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2012 

02/03/2012 
 

 
08/01/2013 

09/30/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/29/2012 

03/16/2012 
 

 
11/01/2013 

01/31/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
05/01/2012 

06/27/2012 
 

 
03/01/2014 

04/30/2014 
100   

 


Begin Construction Phase

End Construction Phase
07/30/2012 

12/31/2012 
 

 
05/01/2014 

12/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2012 

12/31/2012 
 

09/15/2015 
01/01/2015 

04/30/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$731,088
Current Approved:
$731,088
Actual Expenditures:
$731,088

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31